Specified Water Infrastructure Projects: Key takeaways from Ofwat’s 2026 draft SIPR guidance

July 3, 2026
Article posted by: Steve Gummer, Sophie Read
Introduction

The Water Industry (Specified Infrastructure Projects) (English Undertakers) Regulations 2013 (“SIPR”) create a framework allowing large or complex water infrastructure projects to be delivered by a separately licensed infrastructure provider (“IP”) rather than the water company. This reflects the scale and complexity of such projects, which can otherwise threaten the water company’s ability to meet its statutory duties and affect financeability and customer value.

Under SIPR, a project is “specified” when it meets a test which reflects the complexity and size of the project and risk to the water company. The water company is not permitted to carry out the specified infrastructure project itself and must put the project out to tender. The project is then completed by a ring‑fenced IP which receives financing from investors, a Project Licence from Ofwat, and revenue from the water company.

The SIPR draft guidance (“the guidance”) applies to infrastructure projects which have not yet been specified and, therefore, provides a baseline for future projects. Ofwat has incorporated learnings from Thames Tideway into the guidance, with deviations from this model explained.

The guidance aims to provide confidence in the regulatory framework, set out default starting positions and facilitate justified flexibility. The clarity and certainty, coupled with the flexibility to accommodate project‑specific features where appropriate, should support clear risk pricing and reduce inefficiency in delivery and financing, while maintaining customer protection and accountability for outcomes.

Key aspects of the draft guidance

Regulatory Framework
SIPR enables certain risks of large and complex water infrastructure projects to be transferred to a ring‑fenced IP. The water company must not deliver the project itself and must tender it to an IP, meaning the project must be technically discrete to allow third‑party delivery and ensure value for money. The scope of the specified works must be clearly defined to provide bidder certainty and ensure the water company does not complete works designated to the IP. Water companies may carry out genuinely preparatory works (e.g. site surveying), provided these do not overlap with the IP’s scope.

The guidance states that changes to the water company’s water licence will be required. Ofwat expects the Thames Tideway model to provide a starting point, with project‑specific tailoring as needed, including, for example, amendments to Condition B (charging).

For the IP, conditions in the Project Licence will cover delivery, operation and maintenance obligations, the economic regulation framework, ring‑fencing, information requirements and dispute resolution, among other matters. Ofwat provides an indicative Project Licence structure reflecting differing risk profiles across the Construction, Initial Operational and Ongoing Operational periods. The goal of this structure is to ensure that the regulatory framework is stable while the IP is operating at a steady state but is also tailored enough to manage the construction phase. The main body of the Project Licence will consist of enduring conditions regulating the IP throughout the project lifecycle, covering areas such as Allowed Revenue, ring‑fencing and governance. It will also include time‑limited provisions for the higher‑risk construction and commissioning period, for example phase-specific Allowed Revenue calculations, and trigger‑specific conditions activated in defined circumstances (e.g. to protect customers). The guidance provides detail on Allowed Revenue in the Construction and Initial Operational Periods. The guidance adopts a building‑block approach for these higher‑risk phases, combining return on capital, liquidity, and mechanisms for cost recovery, risk adjustment, reconciliation and incentives to support delivery and cost control while maintaining a predictable, financeable revenue stream. It also requires non‑revenue conditions (e.g. governance, timelines and assurance) to ensure Ofwat has visibility of risks, customer protection and delivery.

The guidance also sets out the framework’s approach to regulatory governance. A Liaison Committee (including key stakeholders and supported by an Independent Technical Adviser) oversees the project through regular reporting and meetings, providing independent scrutiny of cost, schedule and risks to protect customers and ensure delivery stays on track.

The final key aspect of the regulatory framework is special administration. Under the Water Industry Act 1991, a special administration order may be made where a water company breaches its duties or is insolvent, to ensure duties are met or to manage financial failure. For IPs, the principal duties will be set out in the Project Licence.

Approval Process
The SIPR framework uses gate approvals separated into stages for development, delivery and operations. Additionally, Ofwat will have an independent assurance framework. This formal oversight of the project supports the credibility of the proposed model and aids early identification of weaknesses.

Procurement Approach
The key features of the procurement approach set out in the guidance are the late-stage IP appointment, the split procurement model and the shadow IP.

Under the late-stage model, which Ofwat sets out as the default, the water company completes most of the preparatory works before the IP is appointed. This is beneficial because procurement of the IP occurs at a stage where the project is more mature and there is more certainty for investors, which improves financeability.

Ofwat expects the split procurement model to be the default. In this model, the works contract is procured separately and prior to the financing procurement. Therefore, the finance is only procured once the scope and risk are more stable. Additionally, this allows financing to be procured from more specialist capital providers, reflecting the capital‑intensive nature of the projects, without allowing financing terms to constrain works development.

As a default, a shadow IP is expected to be used. A shadow IP is a pre-established, effectively operational version of the IP that the water company sets up before the licence is awarded, so it can be transferred to the IP as a ready‑to‑run entity at financial close. Its purpose is to reduce transition and execution risk by ensuring that governance, management, systems and processes are already in place, making the project more stable and therefore more credible and bankable for investors from day one.

Value for Money Assessment
The guidance sets out that the value for money assessment will take place early in the procurement process and will use preliminary information on costs, financing and delivery, which will be compared to the two main alternatives to SIPR: in-house and DPC delivery. The guidance highlights that the assessment will be predominantly qualitative and forward‑looking and will extend to the impacts on the water company’s existing activities.

Risk Allocation
The water company is expected to identify material risks across the project lifecycle and structure the commercial arrangements such that risk is allocated to the party best able to manage and price it. Risk is only expected to be shared between the water company and the IP where it is unmanageable and there are clearly defined protection mechanisms in place.

The risk profile of the project is crucial to customer value. Therefore, Ofwat proposes that the starting position should be to approach risk and incentives in a similar way to a long-life regulated utility asset, which supports bankability and widens the pool of investors.

Furthermore, risk allocation will vary across the different stages of the project. The guidance includes indicative tables setting out the expected risks at each stage (project development, project design, construction, testing and commissioning, and operation and maintenance) of the project and to whom the risk is allocated. For example, contractor default risk during the construction phase would sit with the customer, the IP and the contractors.

Clarity and certainty of risk allocation is a key feature of SIPR and benefits both investors and customers.

IP Charging
The IP charging model sets out how the IP recovers Allowed Revenue and how project costs flow through into customer bills.

The IP is not expected to bill customers directly and the default position will be a pass‑through model. Under this model, the IP charges the water company, which recovers these costs from customers. Ofwat sets out that the IP charge is expected to be constrained by Allowed Revenue and must not exceed the permitted recovery under the Project Licence.

Ofwat will expect the charging model to operate on a predictable annual cycle that aligns with the water company’s charging timetable, along with in‑year settlement mechanisms.

The guidance sets out Ofwat’s approach to stress cases such as inflation, bad debt risk, counterparty credit risk and direct charging as a last‑resort mechanism in cases of water company distress.

The guidance focuses on ensuring a stable and reliable payment mechanism for the IP, addressing stress issues with the aim of supporting predictable, recoverable revenue over the life of the asset and, therefore, greater investor confidence.

Bulk Supply Agreements
The guidance recognises that SIPR projects may underpin bulk transfers and sets out that the default model is a lead‑party model, where one water company procures and interfaces with both the IP and the benefiting water company.

Contractual Framework
The contractual framework governs project delivery, so Ofwat will scrutinise these contracts as the key mechanism for allocating, managing and pricing risk. In particular, it will focus on financeability, interface risk allocation and alignment with the Project Licence. The guidance includes an indicative set of documents and core risks for a late‑stage SIPR project.

Conclusion and takeaways

Ofwat’s draft SIPR guidance seeks to provide a clearer, more structured and financeable framework for major water infrastructure projects, while retaining flexibility for project‑specific features. For investors and lenders, the combination of defined risk allocation, predictable Allowed Revenue and robust regulatory oversight is intended to support confidence, improve bankability and reduce delivery risk, while maintaining strong customer protections.

This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any of the issues raised in this article, please contact us today by telephone or email enquiries@sharpepritchard.co.uk.