Our previous article in the SSES licence series mapped the scope of the new licensing regime and considered which entities are likely to require a load control licence.
This week’s article focuses on the application process itself and offers practical guidance for businesses likely to be affected. For information, Ofgem’s draft load control licence application form can be found here.
1. Application process at a glance
- Applicants will be required to submit Ofgem’s standard electricity licence application form, which has been amended to include the load control licence, with evidence to support each applicable question. Which questions apply will depend on the type of applicant and the application pathway (set out in section 2 below). Following consultation feedback, Ofgem has framed the load control questions at a higher level. The evidence Ofgem expects is unchanged, but the detail will now be set out in separate licence application guidance. Applicants should review that guidance carefully once it is published and before the application window opens.
- Ofgem will review the application and may request clarification or further information, particularly where it identifies compliance concerns. Ofgem will then either grant or refuse the licence. If Ofgem does not make a decision on a complete application within nine months, the licence will be deemed granted through tacit authorisation (see section 5 below).
- Not every applicant will be required to provide the same evidence. To avoid duplication and ensure proportionate scrutiny, Ofgem has created three pathways for the Flexibility Service Provider (FSP) activity, depending on whether the applicant already holds an electricity supply licence. The pathways do not reduce the application requirements for Load Controllers.
- Application fees: All applicants will pay the same fees, regardless of any licence they already hold. The fee is £1,100 for a licence covering either the FSP or the Load Controller activity, or £1,650 for both. Adding an activity later costs £825 (extension) and removing one costs £550 (restriction). Businesses that expect to carry out both activities may therefore benefit from applying for both at the outset.
2 . Application Pathways
To support the emerging consumer-led flexibility market, Ofgem has decided to adopt a proportionate approach to licensing. The application pathways therefore reflect the fact that some applicants have already undergone regulatory scrutiny: electricity supply licence holders will have been assessed against requirements relevant to much of the consumer-facing FSP activity. The level of scrutiny required will depend on whether the applicant holds a non-domestic-only licence or a licence covering both domestic and non-domestic customers. Alongside reduced evidence requirements, eligible suppliers will benefit from targeted derogations from certain load control licence conditions. Ofgem intends to issue these on a class basis, so individual companies will not need to apply for them separately.
There are three application pathways, depending on whether the applicant holds an electricity supply licence and, if so, which type:
- Pathway A: FSP applicants that do not hold an electricity supply licence;
- Pathway B: FSP applicants that hold a non-domestic-only electricity supply licence; and
- Pathway C: FSP applicants that hold an electricity supply licence for both domestic and non-domestic consumers.
| Pathway | Description |
Pathway A: FSP applicants that do not hold an electricity supply licence | Pathway A applies to organisations that are not licensed suppliers, including those already undertaking load control activities before the application window opens. They will be subject to the full evidence requirements because they have not previously undergone regulatory scrutiny. Ofgem will support them through the process with guidance and worked examples. This route is unchanged from the consultation. |
| Pathway B: FSP applicants that hold a non-domestic-only electricity supply licence | These applicants will be derogated from the financial and management control licence conditions (the financial responsibility principle and the ongoing fit and proper requirement) and will not need to provide evidence against the corresponding application questions. They must still comply with, and provide evidence against, the consumer protection conditions. Ofgem’s reasoning is that non-domestic supply licences do not contain sufficiently aligned consumer protections, in particular because the load control licence extends consumer protections to small business consumers.
This approach applies only where the applicant is the same legal entity as the supply licence holder and Ofgem does not identify any existing compliance concerns in relation to the supply licence. |
| Pathway C: FSP applicants that hold an electricity supply licence covering both domestic and non-domestic consumers | Eligible Pathway C applicants will be derogated from the financial and management control conditions and from the consumer protection conditions (treating customers fairly, recommending a suitable service, allowing customers to exit a service and ensuring exit fees are proportionate), and will not need to provide evidence against the corresponding application questions. Pathway C applies only where:
|
Applicants should not treat Pathways B and C as guaranteed. Ofgem will apply derogations on a risk-based and discretionary basis, and retains the ability to require full compliance at the application stage on a case-by-case basis where concerns are identified, and to amend or withdraw derogations if monitoring reveals new risks.
Suppliers relying on Pathway C will also be expected to give consumers clear and specific information about FSP-related activities, including the implications for switching. The pathways do not remove the need to hold a load control licence, nor do they affect Load Controller-specific requirements on cyber security and grid stability.

3. Supporting Information – what evidence is Ofgem expecting?
| Information Type | Description |
| Standard questions | The application will include standard questions, including on company structure, ownership and any other licences held. These questions must be answered by all applicants, regardless of applicant type or pathway. |
| Suitability to hold a licence | Applicants will be required to:
Eligible Pathway B and C applicants will be exempt from the fit and proper questions, but all applicants must still sign the declaration. |
| Operational capability | Applicants will be required to answer questions regarding the following:
Eligible Pathway B and C applicants will be exempt from these application questions. |
| Commencing licensable activity | Applicants will be required to provide a statement of intent setting out the steps the applicant will take to comply with:
Only Pathway C applicants will be exempt from this question, and only in respect of the consumer protection statement. Licensed suppliers that operate, or plan to operate, as a Load Controller must still provide a statement of intent to comply with grid stability requirements. |
| Load control licensable activity | Applicants will be required to specify which licensable activity or activities they will undertake as a:
This requirement applies to all applicants, regardless of pathway. The draft form also asks all applicants to state whether the application relates to domestic consumers, small business consumers or both. |
| Financial responsibility | Applicants are required to provide evidence of financial viability, which may include proof of funding, funding sources and financial forecasting. Eligible Pathway B and C applicants do not need to provide this evidence. |
| Consumer protection requirements | FSP applicants must provide a statement of intent setting out how they will comply with the consumer protection conditions. Ofgem has now published its final Load Control Consumer Protection Guidance, largely as consulted on, which covers treating customers fairly, transparency, complaints handling and support for vulnerable consumers. The final version clarifies that FSPs are expected to give consumers clear and specific information about the implications of signing up their device with another provider, including for switching. Ofgem notes that the guidance “remains an advisory document and the licence itself is the enforceable regulation”, but applicants should use it as the benchmark when preparing their statement of intent. Pathway A and Pathway B applicants must provide this evidence. Eligible Pathway C applicants are not required to do so. |
| Cyber security requirements | Cyber security requirements apply only to Load Controllers, including licensed suppliers. Applicants must describe their approach to risk management, their alignment with government expectations and recognised standards, and how they will assure ongoing cyber security controls. They must also submit a self-assessment against the relevant Cyber Assessment Framework (CAF) profile (Tier 1 for 300MW or above, or Tier 2 for below 300MW) and a statement of intent to comply within the government’s timelines. If the CAF profiles have not been finalised when an application is submitted, applicants should assess themselves against the National Cyber Security Centre’s generic CAF guidance. Based on the draft form, applicants should also be ready to list the systems, software and infrastructure they will use; provide their current aggregate load and a forecast for the next two years; name a Cyber Responsible Officer (and any deputies) and describe their escalation routes; and list any existing cyber security accreditations. Independent assurance reviews are not required at the application stage, but must be carried out annually once the licence is granted. Load Controllers at or above 300MW are expected to be designated as Operators of Essential Services after grant, at which point the NIS regime will replace the cyber security obligations in the licence. |
4. How much scrutiny should applicants expect?
Ofgem may engage with applicants during the assessment to clarify information and allow proportionate updates, but material changes may require a new application. Ofgem will assess all applications itself in the first year; after that, the Security Governance Group will carry out the technical cyber security assessment and make a recommendation, although the licensing decision will remain with Ofgem.
Applicants should also be prepared for further requests. The draft form includes a second tier of information that Ofgem may request where it identifies a need for further scrutiny, including certified copies of official documents, evidence of contact with code administrators, bank, solicitor and auditor details, corporate records, directors’ CVs and identity documents, criminal record certificates for directors and senior individuals, and agreement to attend an interview. Having these to hand can help avoid delay, particularly for applicants relying on the three-month window to secure continuity.
As Ofgem puts it, “submitting an application does not guarantee a licence will be granted”, and Ofgem may refuse an application where the requirements are not met. Where an application is refused on cyber security grounds, applicants will be given reasons and the opportunity to make representations.
5. Tacit authorisation
Tacit authorisation is a notable feature of the regime and a change from Ofgem’s consultation position, made in response to industry concerns about a potential cliff edge for existing operators. If Ofgem has not determined a complete application within the specified period, initially nine months, the licence will be “deemed granted” under regulation 19(5) of the Provision of Services Regulations 2009. Ofgem will keep this processing period under review.
Existing operators may continue without a licence during the 12-month transition period, which is intended to start when the application window opens on 1 March 2027; after it ends, carrying out licensable activities without a licence will be an offence. To be assured of continuity, they must submit a complete application within the first three months of the window opening.
6. Takeaways
Organisations should identify their application pathway early and confirm which activities (FSP, Load Controller or both) they will undertake. Pathway A applicants face the fullest evidence requirements, and Pathways B and C apply only where certain conditions are met, including that the applicant is the same legal entity as the supply licence holder. All applicants should watch for Ofgem’s licence application guidance. FSPs should prepare their statement of intent against the final Consumer Protection Guidance, and Load Controllers should start their CAF self-assessment now. Existing operators should submit a complete application within three months of the window opening, which is intended to be 1 March 2027 (subject to Parliamentary approval).
Looking ahead: the next article in this series will explore cyber security in more detail, along with ongoing compliance requirements and the potential consequences of non-compliance.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any of the issues raised in this article, please contact us today by telephone or email enquiries@sharpepritchard.co.uk.